装配式剪力墙全过程—灌浆套筒剪力墙体系(动态图)

近年来, 国家对装配式建筑的装配率要求在不断提升,特别是在预制率达30%以上的项目中,预制剪力墙已成为装配式建筑的必要选项之一。现阶段装配式建筑的施工及检测体系的不够完善,导致普通的预制剪力墙竖向钢筋连接的施工速度较慢。同时施工过程无法使用仪器进行检测,只能依赖施工人员的专业素质和监理人员的责任心来加以管控,严重制约了预制剪力墙的实际应用。为了改善这一现象,让我们一起学习“装配式剪力墙全过程——灌浆套筒剪力墙体系”完整的施工工艺,在日后的施工过程中有效的提高施工质量。吊装准备 在基础施工完成后,根据轴线控制点引测轴线、控制线、预制墙板边线
//upload-images.jianshu.io/upload_images/16218175-ef34d31dc1b1c639


通过预留孔将控制线逐层往上引测,然后弹出各层轴线及预制墙板边线
//upload-images.jianshu.io/upload_images/16218175-835d9794d252d965



//upload-images.jianshu.io/upload_images/16218175-90d49c77657d14b4



//upload-images.jianshu.io/upload_images/16218175-fe49e07f0540bd02


采用悬挂钢尺法传递高程
//upload-images.jianshu.io/upload_images/16218175-147495144b3a219f



//upload-images.jianshu.io/upload_images/16218175-aba4968ca54e5543



//upload-images.jianshu.io/upload_images/16218175-20da924da29384d7


在内外墙板的结构受力层上放置两组垫块,通过水准仪复合标高
//upload-images.jianshu.io/upload_images/16218175-d2fd64cae78ad1c4


清理插筋上的水泥浆及铁锈
//upload-images.jianshu.io/upload_images/16218175-815521c241212d8a


采用定位工装对插筋进行检验和调整
//upload-images.jianshu.io/upload_images/16218175-769541f9de973537



//upload-images.jianshu.io/upload_images/16218175-accc436a5d664992


安装橡塑棉条
//upload-images.jianshu.io/upload_images/16218175-61ccc2c1971acfa5


墙板就位前应在待吊装位置准备斜支撑
//upload-images.jianshu.io/upload_images/16218175-be2eeff9fa37b84c


根据设置要求配置砂浆,其强度等级不应低于被连接构件的混凝土强度等级
//upload-images.jianshu.io/upload_images/16218175-d861b554fc561de0


竖向构件吊装 预制剪力墙安装采用底部坐浆法,其厚度不宜大于20mm
//upload-images.jianshu.io/upload_images/16218175-f4c05662d7911cae


调整平衡梁方向,并使平衡梁中心与墙板重心标示基本在一条直线上
//upload-images.jianshu.io/upload_images/16218175-88c4420691a8fb29


挂钩(PC构件卡扣内部结构、埋件)
//upload-images.jianshu.io/upload_images/16218175-2f89da3636c9c30c



//upload-images.jianshu.io/upload_images/16218175-5f2a12b62eea789c


开始起吊时,应将构件调离地面200~300mm后停止起吊,并检查起重机的稳定性、制动装置的可靠性、构件的平衡性和绑扎的牢固性等,待确认无误后,方可继续起吊。已吊起的构件不得长久停滞在空中。(水平夹角不宜小于60度,且不应小于45度)
//upload-images.jianshu.io/upload_images/16218175-8c2400469321642a



//upload-images.jianshu.io/upload_images/16218175-9b84be7d024ec982



//upload-images.jianshu.io/upload_images/16218175-fc5ad11959b0f559


当构件吊至安装平面上方80~100cm处,吊装工人扶助墙板,缓缓降低,将墙板与边线和端线靠拢
//upload-images.jianshu.io/upload_images/16218175-674a8be13f7cadd5



//upload-images.jianshu.io/upload_images/16218175-65ef81f527673109


离地12~15cm时,使用镜子观察,将灌浆套筒孔与地面插筋对齐插入
//upload-images.jianshu.io/upload_images/16218175-8c57be3d3cf1e26b


墙板就位后,安装长、短斜支撑,墙板位置通过短支撑调节,垂直度以一根长斜支撑调整为准
//upload-images.jianshu.io/upload_images/16218175-c0647b0da9890a63


待校对完毕后紧固另一根,不可两根均在紧固状态下调整
//upload-images.jianshu.io/upload_images/16218175-325904b64fc0f386


用靠尺和塞尺测量相邻墙面的平整度
//upload-images.jianshu.io/upload_images/16218175-f901b57aeabfb3f7


取钩、移位
//upload-images.jianshu.io/upload_images/16218175-7266f027a2ced8ef



//upload-images.jianshu.io/upload_images/16218175-e13551fb0c559652


现浇节点钢筋绑扎 在接缝处粘贴防水卷材、填充挤塑板
//upload-images.jianshu.io/upload_images/16218175-96b3015cef1351d5


安装箍筋、安装纵筋、钢筋绑扎
//upload-images.jianshu.io/upload_images/16218175-6aebdf86002c2195


现浇节点支模 垫块放置并找平
//upload-images.jianshu.io/upload_images/16218175-bad8b26342a8bb5d


铝模板之间用销钉及螺栓连接
//upload-images.jianshu.io/upload_images/16218175-5d619e37f0d02016


固定铝模板
//upload-images.jianshu.io/upload_images/16218175-deeb2a426ccab3c6



//upload-images.jianshu.io/upload_images/16218175-71225908d4797a6a


叠合楼板吊装 搭设临时支撑
//upload-images.jianshu.io/upload_images/16218175-bb3417c4e5cab0d7


标高调整
//upload-images.jianshu.io/upload_images/16218175-e1d0690e2bd01810


楼板挂钩、起吊移板
//upload-images.jianshu.io/upload_images/16218175-01f22ed79cd18cca


楼面接缝模板安装
//upload-images.jianshu.io/upload_images/16218175-5db7b16299c2dc55



//upload-images.jianshu.io/upload_images/16218175-abfe70f94ee61c07


楼面水电预埋
//upload-images.jianshu.io/upload_images/16218175-197a8bada422a08b


楼面钢筋绑扎
//upload-images.jianshu.io/upload_images/16218175-24e725ae9ad3b270


现浇混凝土施工 混凝土浇筑前洒水湿润
//upload-images.jianshu.io/upload_images/16218175-826e67260e2fa53f


浇筑混凝土
//upload-images.jianshu.io/upload_images/16218175-1385d295a2c49465


混凝土养护
//upload-images.jianshu.io/upload_images/16218175-f87b25de34d41cff


套筒灌浆施工 灌浆料制造时称量适量的自来水和灌浆料干粉,将灌浆料倒入搅拌桶内,边搅拌边加水,搅拌均匀后静置排气
//upload-images.jianshu.io/upload_images/16218175-586f0bb023d5a1ce


灌浆料流动性检测时,将适量的灌浆料倒入流动性测量其中,提起模子,测量灌浆料平摊后最大直径是否符合要求
//upload-images.jianshu.io/upload_images/16218175-74cf56c8d9548e6a



//upload-images.jianshu.io/upload_images/16218175-5b81bfd416410007


套筒灌浆前应制作灌浆料试块(待终凝后,终凝时间为水泥加水拌和到水泥浆完全消失可塑性,并开始产生强度的时间,约5~8小时。)
//upload-images.jianshu.io/upload_images/16218175-eaeb4ab7aec74fea


灌浆套筒抗拉试验(按不超过1000个灌浆套筒为一批,每批随机抽取3个灌浆套筒制作对中连接接头试件标养28D)
//upload-images.jianshu.io/upload_images/16218175-ac45e0120e467233


灌浆作业采用压浆法从下口灌注,当浆料从上口流出后及时封堵
//upload-images.jianshu.io/upload_images/16218175-d61a6f8db6920423



//upload-images.jianshu.io/upload_images/16218175-e8c96a2c8bc1032f


楼梯休息平台安装 休息平台板吊装
//upload-images.jianshu.io/upload_images/16218175-9b1b53744ea07882


梯板吊装
//upload-images.jianshu.io/upload_images/16218175-e6cd59ee8ce0d732


外墙接缝处理 预制构件安装时角度存在偏差,将错台处高出部分用角向磨光机打磨掉
//upload-images.jianshu.io/upload_images/16218175-a8ef51b424acaa6f


对预制构件在运输、吊装过程中出现边角破损进行修补
//upload-images.jianshu.io/upload_images/16218175-3d38486a0ff033b4


                   处理接缝宽度并满足设计要求
//upload-images.jianshu.io/upload_images/16218175-5150731d5e39dc4d


接缝内异物处理
//upload-images.jianshu.io/upload_images/16218175-26c489290a707cb4


接缝内填充泡沫条
//upload-images.jianshu.io/upload_images/16218175-16d17f38685f862c


接缝周边粘贴美纹纸
//upload-images.jianshu.io/upload_images/16218175-3a6a1b1e7990f7d9


涂刷底涂
//upload-images.jianshu.io/upload_images/16218175-5b4328dd037600e2


胶嘴用美工刀45度角切割,然后施胶
//upload-images.jianshu.io/upload_images/16218175-d564a2c5efca5433


至此,所有的工序全部完成。
//upload-images.jianshu.io/upload_images/16218175-db8ff670dc09c370


装配式剪力墙结构,采用大量水平和垂直的预制混凝土构件,包括预制楼板、预制墙体、预制楼梯等,通过“搭积木”的方式将建筑物建成,并经工程实践形成本工法。这一方法的主要优势是提高了观感质量、缩短了施工工期、节省了周转材料,更为重要的是由于大型吊装机械的应用,使得劳动力的使用数量大大减少,有效地缓解了“用工荒”的压力,具有良好的经济效益和社会效益。海南省BIM中心致力于海南省BIM事业的发展,率先在海南省内开展BIM培训,BIM网站,BIM设计,BIM造价,BIM全过程管理、BIM+GIS\FM\VR\AR\大数据\云计算\智慧城市的探索,为海南省建筑信息化作出自己的贡献。我们的网站是www.xycost.net。长按下面的二维码有惊喜哟>_<~